Viewing the Activity
From the Case Display screen under the Case Progress Summary tab, right mouse click over an activity. Click on View.
Completing an Activity
1. From the Case Display screen under the Case Progress Summary tab, right mouse click over an activity and click on Update Activity
2. The Update Activity screen will pop up. From the drop down menu, change the Status to Completed
3. Update the completed on field to specify the date and time the activity was completed.
Activity Progress Summary1. From the Case Display screen you are able to see the activity progress summary by clicking on the Activity Progress Summary tab